Commission Final Order
- that the Sierra Club Petition for Reconsideration is denied;
- that Mr. Hildebrand's Petition for Reconsideration is denied;
- that the TrAILCo Petition for Reconsideration is granted as described in this Order;
- that the sixth ordering paragraph of the Final Order, regarding installation of a static VAR compensator, is rescinded;
- that TrAILCo notify the Commission within 30 days of the date the MVAR described in this order is installed and operational at the Meadowbrook substation;
- that TrAILCo may proceed with a phased approach to construction and complying with the pre-construction conditions of the Final Order, as described in this Order;
- that the eleventh ordering paragraph of the Final Order is revised;
- that the H-P Petition to Intervene Out of Time and Petition for Reconsideration are denied;
- that Ms. Stahl's Petition for Reconsideration is denied;
- that the Sierra Club Petition for a Continuing Prudence Review is denied;
- that Mr. Hildebrand's Petition for Additional Hearing is denied;
- that exept as modified, the Order of August 1, 2008 remains the final order of the Commission in this matter;
Case Final. Removing from open docket.